Chuy:
I have attached a crude drawing of a cross-sectional view of the hull and
deck joint. As you will see, the sealant goes in the space between where the
hull and deck overlap. Ideally it would be best to remove the rivets in
order to open the gap in order to remove the sealant. That requires the
removal of the rub rail and chances are that the rail will be destroyed in
the process. Once the sealant is forced into the gap the gap is closed with
new rivets or bolts. You would do this in sections rather than all at once.
The easier alternative is to just remove whatever sealant you can from the
join and add sealant at the bottom of the gap but that will be a temporary
fix based on my experience. 

I can't see where putting sealant on either side of the rub rail would
accomplish much of anything other than make a mess. It is the gap that needs
to be sealed, not the rub rail.

The rivets on my deck hull join held firmly for 35 years but if I were to
replace them I would probably use bolts and at closer intervals to give less
movement to the join area. But I have already glassed the join on the inside
so any hardware is probably redundant anyway.

I will be interested to see what Rummy's strategy is.

Graham 




hull-deck join.jpg
See the original archive post
×

Message to Webmaster:

To use your email application to send a messsage to the webmaster rather than this form, .



×

Post to the Rhodes 22 Email List:



×

Sending Post:

Your post is being sent... waiting